Slowly, things seem to be moving forward with the detailed plan. The overview page is new at CABN:
View attachment 90026
www.lansstyrelsen.se
===>
Proposal for a detailed plan for Stenbrottet 2:1, Nunasvaara södra
The purpose of the detailed plan is to enable mining operations at the Nunasvaara graphite deposit in Vittangi, Kiruna municipality.
View attachment 90027
Overview map: the planning area is illustrated with a solid red line. Click on the image for larger format.
Map viewer of the planning area External link, opens in new window.
The Government has decided to give the County Administrative Board of Norrbotten County the task of producing the proposal and otherwise doing the work needed under the Planning and Building Act to enable the adoption of a detailed plan that enables mining operations within part of the property Stenbrottet 2:1 and others, in Nunasvaara Kiruna municipality. The plan proposal must be reported to the Government Offices as soon as possible.
The Government's decision pdf, 235.9 kB.
The County Administrative Board will develop a detailed plan that enables graphite mining, Government Offices External link.
The detailed planning work will take place in partial stages
The planned mining area consists of the Niska South, Niska North, Nunasvaara South and Nunasvaara North deposits. The County Administrative Board has deemed it appropriate to divide the detailed planning work into two stages, Nunasvaara South and Nunasvaara North.
Deletapp 1, Nunasvaara södra
Work is now underway to develop a proposal for a detailed plan for sub-stage 1, Nunasvaara South. The preliminary drainage of the planning area includes the area where the company has already been granted an environmental permit and the road area up to the E45 (part of Nunasvaaravägen).
Stage 2, Nunasvaara North
Stage 2 consists of
Niska South, Niska North and Nunasvaara North. The County Administrative Board is investigating how planning of the area can be carried out in the best way.
Planprocess
The work on the detailed plan is conducted with an extended procedure in accordance with the provisions of the Planning and Building Act. For more information on what the planning process looks like in an extended planning procedure:
The process for extended procedure, PBL knowledge bank, Boverket External link.
The planning process began in 2020 by Kiruna municipality. A proposal for a detailed plan for the area has been shown for consultation in 2021 and review during May-June 2025. As the main purpose and conditions of the plan proposal have not changed, we assess that the planning process that has begun can continue.
New legislation
Due to changes in the legislation, we assess that previous environmental assessments need to be supplemented in order to meet formal requirements.
A decision on a supplementary investigation and delimitation consultation will be made shortly.
for the links go directly to the page (link s.b.)
Frequently asked questions
Here you can find answers to the most frequently asked questions regarding the planning process. Our aim is to maintain clarity and transparency during the work. If you can't find the answers you're looking for, please contact us.
View attachment 90029
Detaljplanens syfte är att möjliggöra gruvverksamhet vid grafitfyndigheten Nunasvaara i Vittangi, Kiruna kommun.
www.lansstyrelsen.se
To get all the information, please go to their page and have the site translated.
I wish you all a wonderful weekend.
______
View attachment 90034
Better late than never. Sorry that I briefly dozed off out of boredom and therefore missed the update regarding the detailed plan.
Notification
The County Administrative Board has, on behalf of the government, prepared a proposal for a detailed plan for part of the property Stenbrottet 2:1 etc. Nunasvaara stage 1 in Kiruna municipality. The plan proposal is under renewed review and is available between 3 October and 3 November to give affected owners and stakeholders the opportunity to submit comments.
Review documents are available in paper form in Kiruna City Hall and the County Administrative Board entrance in Luleå.
See the County Administrative Board's opening hours here. Digital documents can be found under the heading
Review No. 2 .
The review is the last opportunity for those affected to have their say, but also an opportunity to see how comments from the consultation and review 1 have affected the plan proposal.
Comments on the proposed detailed plan must be submitted in writing to the County Administrative Board by sending an email or post:
- Email to: norrbotten@lansstyrelsen.se
- Mail to: Norrbotten County Administrative Board, Urban Planning and Cultural Environment, 971 86 Luleå
Enter the registry number
10666-2025 as well as your name and contact information.
Your comments must be submitted to the County Administrative Board by November 3rd.
Notification letter about review
Review No. 2 - open October 3- November 3
The County Administrative Board's plan proposal is under renewed review and is available between October 3 and November 3 to give affected stakeholders and interested parties the opportunity to submit comments.
Audit documents
Planning basis
- Wastezip, 22.6 MB.
- Noise and vibrationszip, 9 MB.
- Post-processing planzip, 13.2 MB.
- Cultural environmentzip, 22.5 MB.
- EIA environmental permitzip, 9.9 MB.
- Natural environmentzip, 53.8 MB.
- Reindeer nutrition analysiszip, 19.2 MB.
- Socio-economic impact analysiszip, 912.9 kB.
- Aquatic environmentzip, 37.8 MB.
- Area of activityzip, 6.9 MB.
- Stormwater investigationpdf, 3.1 MB, opens in new window.
The review is the last opportunity for those affected to have their say, but also an opportunity to see how comments from the consultation and review 1 have affected the plan proposal.
Comments on the proposed detailed plan must be submitted in writing to the County Administrative Board by sending an email or post:
- Email to: norrbotten@lansstyrelsen.se
- Mail to: Norrbotten County Administrative Board, Urban Planning and Cultural Environment, 971 86 Luleå
Please provide the registry number 10666-2025 as well as your name and contact information.
Your comments must be submitted to the County Administrative Board by November 3rd.
Audit opinion no. 2 and processing
After review no. 2, we will compile the comments received and revise the planning documents if necessary.
The audit report will be sent to those who have submitted comments but have not had them addressed.
..."
Syfte och uppdrag Detaljplanens syfte är att möjliggöra gruvverksamhet vid grafitfyndigheten Nunasvaara i Vittangi, Kiruna kommun.
www.lansstyrelsen.se
I'll just leave that here without comment.
_ _ _ _
I don't know if I've already posted the article:
"The government wants to say yes to mines faster
Updated September 29, 2025Published September 26, 2025
The environmental assessments of new mines, industries, wind farms and nuclear power plants will not be reviewed in the Land and Environmental Court, but in a new authority.
The government wants the new system to begin being implemented as early as July 1, 2027.
According to Minister of Energy and Enterprise Ebba Busch (KD), it is about making environmental assessment more efficient and predictable.
Assessment and permit review will be moved from the county administrative boards' consultation process to the new authority. In the long term, tasks from the land and environmental courts may also be moved there.
According to the investigation, the land and environmental courts could become a review body.
– That way we can have a coherent permit process with one authority, says Ebba Busch.
The proposal is met with criticism
One aim is to be able to meet the requirement that projects designated in the EU's Critical Raw Materials Regulation must receive a permit within 27 months.
There are consultation bodies that are critical of the proposal. However, the Swedish Courts Administration has proposed that the land and environmental courts be closed down completely, which in turn is met with criticism. In a debate article in
Svenska Dagbladet , three lawyers write that implementing the change is a waste of resources and risks losing expertise.
However, the government decided on September 19 to proceed with the inquiry's proposal. And assuming that it is also the Riksdag's decision, the changes will be implemented in stages, starting on July 1, 2027."
Miljöprövningarna av nya gruvor, industrier, vindkraftparker och kärnkraftverk ska inte prövas i mark- och miljödomstolen, utan i en ny myndighet. Regeringen vill att det nya systemet ska börja införas redan den 1 juli 2027.
www.svt.se