Monkeymandan
Regular
@beserk I found it in Finland!
part o the verdict:
24 Conditions
"General condition
1.) The business must be conducted, facilities designed and work carried out in main accordance with what the company has stated in the application documents and has otherwise stated or undertaken in the case, unless otherwise stated in this judgment.
Explosions
2.) Blasting in open pits may only be carried out on weekdays during the day between 07.00-18.00 after a predetermined time and after a clear audible warning signal. Nearby residents who wish to do so must be informed about times for blasting.
3.) Blasting in the open pits must be carried out so that vibrations in the nearest homes are minimized. Vibrations as a result of blasting in the open pits must not result in a higher oscillation speed in the vertical direction in the housing's supporting basic structure such as plinth or plinth than 5 mm/s in more than 5% of the blasting occasions per calendar year and never exceed 7 mm/s.
Control of ground vibrations must take place at each blasting occasion by measuring at a nearby residential building. Measurement must comply with SS 4604866:2011.
4.) Air shock waves resulting from the blasts in the opencast mines must not exceed 100 pascal free field value in more than 5% of the blasting occasions per calendar year and must never exceed 200 pascal. Control of air shock waves must take place at each blasting occasion by measuring at a nearby residential building. Measurement must follow SS 02 52 10.
Noise
5.) Noise from construction work other than particularly noisy construction work (such as drilling, rock knocking and piling) must not give rise to a higher equivalent noise level at homes than
Non-holiday Monday – Friday (day) At 07.00-19.00 60dBA Weekend off Monday – Friday (evening) At 19.00-22.00 50 dBA Saturday, Sunday and holiday (day) At 07.00-19.00 50 dBA Saturday, Sunday and holiday (evening) At 19.00-22.00 45 dBA At night At 22.00-07.00 45 dBA
Particularly noisy construction work may only be carried out on weekdays at 07.00-19.00.
6.) Noise from the activity must not give rise to a higher equivalent noise level at homes
Non-holiday Monday – Friday (day) At 06.00-18.00 50 dBA
Night time At 22.00-06.00 40 dBA
Other times 45 dBA
Work steps that can typically result in instantaneous noise levels above 55 dBA in homes may not be carried out at night.
Control must take place through immission measurements or through near-field measurements and calculations. An initial check must take place within three months from when all parts of the business that may cause noise have been put into operation. Inspections must then take place as soon as there have been changes in the operation that may lead to increased noise levels, but at least once a year.
Chemicals and hazardous waste
7.) Storage of chemicals and liquid hazardous waste may only occur on an embanked and sealed surface equipped with rain protection. The embankment must contain the volume of the largest storage vessel and 10% of the total volume of other storage vessels. The storage must be protected against collision. Spills and leaks must be collected and taken care of immediately.
Dusting
8.) Measures must be taken to limit the spread of dust that may pose a nuisance to human health and the environment.
Reindeer nutrition
9.) The company must annually carry out consultations with Talma Sami village and Gabna Sami village with the aim of minimizing the negative impact of the operation on the reindeer husbandry. The company must provide information in the environmental report that consultations have been held during the year.
10.) During the period from 1 December to 31 May inclusive, the company may not carry out blasting or drilling for production in the open pits, primary crushing of mined ore or transport of ore or waste rock from the open pits.
Release to water
11.) County retention water, contact water and potentially contaminated water must undergo purification before it is allowed to overflow into Hosiojärvi (county retention water from open pits, runoff from industrial areas, ore stockpiles and non-final-covered parts of sand and waste rock reservoirs, leachate from the sand and waste rock reservoir, water from cells for sludge and process water from the concentrator).
Facility
12) Ditches, pump pits, basins and other plant parts that handle the water that is intended to undergo purification must be tight. Relationship drawings must be submitted to the supervisory authority at a time determined in consultation with the supervisory authority.
13) Breakaway masses of moraine and peat and such masses that are otherwise taken out of the business must be used in the business or stored to the extent required for the post-processing of the business and used for this purpose. The company must report to the supervisory authority the planned design of moraine storage before the construction of such moraine storage begins, and must then annually report to the supervisory authority a balance of the amount of moraine stored and consumed.
14) The sand and gravel reservoir must, with the exception of parts of the gravel embankment, be constructed with a foundation consisting of a liner, which is connected to a collecting ditch. Drainage systems must be installed under the respective upper liner and with separation of the respective drainage water. Construction of the sand and gray rock reservoir can take place in stages.
Inspection of completed construction works (complete and in stages) must be carried out by an independent inspector, who is appointed by the company after consultation with the supervisory authority. The inspection report and relationship drawings must be submitted to the supervisory authority at a time determined in consultation with the supervisory authority.
Finishing
15) The waste in the sand and waste rock storage must be covered with a qualified cover. Covering must begin within one year from when the surface, or part of it, is completed to its final form.
16) Backfilling in open pits that are above the equilibrium level for groundwater in the respective open pits must be covered with qualified coverage. Coverage must begin within one year of the completion of backfilling of an open pit.
17) The qualified cover must be designed and carried out with criteria to ensure that the oxygen transport rate through the cover in a normal year is limited to a maximum of 0.5 mol/m 2 and year. The cover must be designed with a 0.5 m thick sealing layer of moraine mixed with bentonite, a 2 m thick protective layer of moraine and a 0.1 meter thick plant establishment layer that is vegetated, or another design that provides an equivalent oxygen transport rate.
18) An implementation description for final post-processing must be submitted to the supervisory authority no later than one year before the operation is planned to finally cease.
Ecological compensation
19) The company must carry out measures to compensate for the loss of natural values that arise through the operation. The compensation measures must correspond to at least 115% of the impact value, calculated according to the CLImB calculation model or a similar calculation model. The compensation area must be located within Kiruna municipality or, alternatively within Norrbotten county. The compensation plan
must be drawn up in consultation with the supervisory authority and submitted to the supervisory authority no later than one year from when the permit has gained legal force and has been used or later if the supervisory authority so allows. The supervisory authority may then decide on compensatory measures.
Species protection
20.) Felling within the area of operation may not take place during the period from May 1 to July 31 inclusive.
Financial security (SEK 1 ≅ € 0.09 ≅ AUD 0.14)
21.) The company must provide financial security for costs for carrying out the restoration measures that the business may cause as follows
a) Basic security must be provided with SEK 140 million (140,000,000). The security must be submitted to the Land and Environmental Court for review no later than three months after the legally binding permit judgment.
b) Security for post-treatment of the sand and gray rock reservoir must be set up in stages so that it finally covers a total of SEK 85 million (85,000,000) as follows
- a security of SEK 30 million (30,000,000) must be submitted to the Land and Environmental Court for review no later than two years after the permit has been claimed,
- security of SEK 25 million (25,000,000) must be submitted to the Land and Environmental Court for review no later than five years after the permit has been claimed, and
- security of SEK 30 million (30,000,000) must be submitted to the Land and Environmental Court for review no later than seven years after the permit has been claimed.
When the basic security according to point a) is to be provided, the amount must be calculated using the consumer price index. When the staged security according to point b) is to be provided, both the basic security and the staged amount/s must be calculated using the consumer price index. January 2020
shall constitute the base month and calculation shall take place against the latest valid consumer price index as of the day the security is submitted to the court.
Control
22.) The company must draw up a special control program regarding conditions 15-17 that ensures and documents that the coverage meets the requirements in condition 17. The control program and relevant relationship drawings must be submitted to the supervisory authority before coverage begins.
23.) A program for self-control regarding the construction phase of planned facilities must be drawn up and reported to the supervisory authority no later than one month before construction work is intended to begin. The control program must specify measurement methods, measurement frequency and evaluation method.
24.) A program for self-control regarding the operation of the business must be reported to the supervisory authority no later than three months before the intended commencement of mining operations. The control program must specify measurement methods, measurement frequency and evaluation method."
link to the PDF (the whole verdict in 191 pages)
_____
Legal fees
The Land and Environment Court rejects the respective claims of Sami Village Gabna and Talma Sami for legal costs.
AN APPEAL.
The Land and Environment Court dismisses the claims of xxx, xxx, xxx and xxx, xxx and xxx for financial compensation due to the mining activity applied.
It only just dawned on me that they didn’t Condition a max limit of ore extraction per year.
I think this means they can in theory front load the ore extraction, eg mine 150ktpa ore per year (or whatever figure), provided they stay within the 24yr LOM total ore limit.
MT alluded to this previously, but I was sceptical and assumed they would include a Condition with max annual extraction.